Just landed
Payroll correctness sweep
14 bugs found and fixed across the payroll pipeline (Sprint 2 verification, May 25). The pay engine is now harder to fool with adjusted clocks, retro back-pay, and CSV submission edge cases.
In flight right now
Caregiver clock-in + EVV
Five stories actively being built: 6-point SANDATA capture, attestation + four sign-off methods, live-in provider transmission, pre-submit OT projection, and home/community categorization for state audit.
Watch this
SANDATA Alt EVV status
Cheryl believes CFMS is already an active Alt EVV vendor; prior planning assumed fresh onboarding. Confirmation request sent to Sandata. Answer determines whether EVV go-live is 2-3 weeks or 4-6 weeks of work.